Search
Close this search box.
Search
Close this search box.

Construction Updates

Complete

From 21 June 2021 Stephens Lane will be closed for vehicle and pedestrian access. It will reopen as a walkway

Complete

On Monday 2 March Fitzgerald Constructions Australia will start early works at South Bank to enable the start of construction

Complete

From Monday 26 August 2019 materials will be lifted from trucks on George Street into the Queen’s Wharf construction site.

Complete

Temporary detour of the Clem Jones Promenade for overhead works on the Neville Bonner Bridge   When: From Monday 10

Complete

From Monday 26 September 2022 for 2 weeks, a temporary pedestrian detour from 6.30am to 6.30pm will be required to

Complete

Night works will continue to 30 September 2022, five nights a week. For safety reasons large exclusion zones are required

Complete

From Wednesday 14 September 2022 for two nights additional lighting and intermittent noise is expected for structural steel works. .

Complete

From Monday 20 June 2022 a temporary footpath closure on George Street adjacent to the Treasury Hotel will be required

Complete

From Monday 1 August 2022 a temporary footpath closure on George Street adjacent to the Treasury Hotel will be required

Complete

From Monday the 29 August 2022 for approximately 5 nights, George and Alice Streets footpaths between Margaret and William Streets

Complete

On Saturday 27 August 2022, out-of-hours works and a temporary traffic detour will be required for works to a tower

Complete

On Saturday 20 August a temporary traffic detour to remove a tower crane from the Queen’s Wharf site will be

Complete

From Friday 29 July 2022 for approximately 4 nights, Alice Street footpath between William and George Sts (on the Queen’s

Complete

On Monday 27 June, Delta Group will commence site establishment to enable early works on Queen’s Wharf Tower precinct. When:

Complete

One day per week, between Monday to Friday from 11am to 4pm for safety reasons, a temporary lane closure is

Complete

On Saturday 25 June 2022, out-of-hours works and a temporary traffic detour will be required for works to a tower

Complete

On Saturday 23 April 2022, out-of-hours works and a temporary traffic detour will be required to climb a tower crane

Complete

Night works will continue through to 1 April 2022, five nights a week. For safety reasons large exclusion zones are

Complete

On Saturday 12 March 2022, a temporary traffic detour will be required to remove a tower crane adjacent to George

Complete

On Tuesday 15 February and Wednesday 16 February 2022 a road closure will be required on Margaret St between William