Construction Updates
Back

Temporary traffic changes to part of George Street (between Mary and Margaret Streets)

From Monday 26 August 2019 materials will be lifted from trucks on George Street into the Queen’s Wharf construction site. For safety reasons, temporary traffic holds will be required on George Street.

When:

From Monday 26 August 2019, tower crane lifts will occur intermittently between 6.30am and 6.30pm Monday to Friday, and some Saturdays, requiring temporary traffic holds on George Street.

Where:

George Street between Margaret and Mary Streets. Traffic in both directions may be affected. See map over page.

What to expect:

From Monday 26 August, temporary traffic holds will be required intermittently. Traffic control will be in place to direct motorists when tower cranes are lifting material into the site from George Street. Best efforts will be made to keep hold times to a minimum, but they could be up to 5 minutes in some instances.