Construction

Construction updates

Stay Informed

 

Destination Brisbane Consortium is the project developer responsible for the design, approval and construction of Queen’s Wharf Brisbane.

Queen’s Wharf Brisbane is the largest construction project in Queensland and at its peak will employ nearly 2,000 people.

The consortium has chosen to break the construction down into multiple contractors for different work packages. These include:

  • Demolition (completed December 2017)
  • Excavation (completed July 2019)
  • Mangrove Walk, Bicentennial Bikeway and Waterline Park (completed September 2019)
  • The Landing structural works (completed September 2020)
  • Neville Bonner Bridge (started March 2020)
  • Shell and core construction of Integrated Resort Development (started July 2019)
  • Internal fit-out of Integrated Resort Development (started July 2021)
  • Public realm including Bicentennial Bikeway upgrade, architecturally designed parks, Velo Café and amenity block (started March 2021)
  • Heritage base works including structural support work (started August 2021)
  • Tower 5 Precinct early works (started July 2022)

Destination Brisbane currently has three contractors engaged – Multiplex, Fitzgerald and Delta Group.

Multiplex is responsible for the main integrated resort development and public realm works along the Bicentennial Bikeway and Queens Wharf Rd and Fitzgerald is responsible for the Neville Bonner Bridge construction.

Standard construction hours are from 6.30am to 6.30pm Monday to Saturday. Currently, Multiplex is approved to undertake night works (excluding Friday and Saturday nights) and outside these hours construction notices are issued and uploaded to the website under construction.

To stay informed about the project and construction activities please subscribe to our monthly e-newsletter or sign-up for construction updates by following the stay informed tab at the top of this page.

Destination Brisbane Consortium is excited to be building this transformational city changing project for Brisbane and we thank the community for their patience while this work is undertaken.

For general enquiries please contact the Consortium direct on 1800 104 535 or email qwbenquiries@destinationbrisbane.com.au.

Slide through to see Queen’s Wharf Brisbane evolve

Construction March 2022

Construction Updates

  1. In Progress

    Night Works: Drill piling works adjacent Bicentennial Bikeway, within the construction site

    From Tuesday 19 September to 18 March 2024 piling operations will be carried out at night-time between the integrated resort and Bicentennial Bikeway, underneath the Riverside Expressway. Bikeway access will be maintained. When: From 19 September to 18 March 2024 works will continue under the Riverside Expressway within the construction site. Work hours will be […]
  2. In Progress

    Night works: Structural steel with exclusion zones

    Night works are continuing five nights a week. For safety reasons large exclusion zones are required for these works when minimal workers are on-site. When: Night works are continuing and are scheduled from 6.00pm to 5.00am Monday to Friday nights until 29 February 2024. These works are in addition to the standard site hours from […]
  3. Completed

    Traffic changes: Northbound Margaret Street off-ramp temporarily reduced to one lane

    On Tuesday 14th November 2023 there will be a temporary lane closure on the northbound Margaret St off-ramp. When: On Tuesday 14th November 2023 between 4pm and 8pm a temporary lane closure will occur on the northbound Margaret St offramp. The lane closure will be reduced until William Street. The temporary lane reduction on Margaret Street […]
  4. Completed

    Night works: Intermittent William St closure between Alice and Margaret Sts

    Rescheduled from Thursday 26 October due to weather. From 6pm on Monday 30 October a temporary traffic detour will be required for works on William St between Margaret and Alice St. When: From Monday 30 October, from 6pm to 6:30am as required. Contingency days following have been approved if the work is not completed in […]
  5. Completed

    Traffic changes: Northbound Margaret Street off-ramp temporarily reduced to one lane

    On Thursday 12 October 2023 there will be a temporary lane closure on the northbound Margaret Street off-ramp. When: On Thursday 12 October 2023 between 4pm and 8pm a temporary lane closure will occur on the northbound Margaret Street offramp. The lane closure will be reduced until William Street. The temporary lane reduction on Margaret […]
  6. Completed

    Night Works – George Street westbound between Charlotte and Mary Street temporarily reduced to one lane for footpath upgrades

    Night works from Monday 9 October to Monday 30 October 2023 to upgrade a section of the George Street footpath. Footpath to remain open to pedestrians during the day. When: From Monday 9 October 2023 works on the southern footpath between Mary and Charlotte Streets (outside the Printery and Treasury Hotel buildings) will take place. […]
  7. Completed

    Temporary northbound Margaret Street off-ramp reduced to one lane for William Street Upgrades

    Night works to take place on Sunday 8 October 2023 to upgrade a section of the William Street footpath outside 1 William St. Temporary diversions for motorists and pedestrians while the northbound off-ramp onto Margaret Street is reduced to one lane and William St is closed. When: From Sunday 8 October 2023 night works and […]
  8. Completed

    Weekend off-ramp closures: Margaret Street

    Works: Southbound Riverside Expressway Margaret Street off-ramp will be closed for motorists on Saturday 7th October between 6am and 4pm. Why: An exclusion zone is being made for works to remove the tower crane from Tower Three. When: Works are for Saturday 7th October between 6am to 4pm. These works are required during daylight hours […]
  9. Completed

    William Street and Miller Park upgrades

    From Tuesday 19 September to Tuesday 3 October 2023 works to upgrade a section of the William Street and Miller Park will commence. Pedestrian access on William Street will not be impacted. When: From 19 September to 3 October 2023 works on William Street and within Miller Park (on the north side of the integrated […]
  10. Completed

    Two-week trial: No right turn onto William Street from Margaret Street

    A temporary no-right turn onto William Street from Margaret Street will be in place for motorists this Thursday for two weeks. When: From 4am Thursday 17 August 2023 a temporary no-right turn onto William Street will be in place for motorists travelling from the Margaret Street Riverside Expressway off-ramps (northbound and southbound) and Gardens Point […]