Construction

Construction of the $3.6B Queen’s Wharf Brisbane development is underway.

Demolition of the non-heritage buildings occurred in 2017 and now in 2018 we are undertaking excavation and shoring activities for the future integrated resort development (arc shaped building) basement.

Basement excavation and shoring work is being managed by Probuild. For any construction, employment or supply opportunities related to this package of work, please contact Probuild direct on: 1800 676 329 or email: queenswharf@probuild.com.au.

The basement excavation and shoring is expected to continue until late-2019 when the site will then be ready for foundations.

In another area of our site, Multiplex has begun work has begun for construction of Waterline Park and the Goodwill Extension area upgrade that will see the transformation of a 500 metres stretch of the Bicentennial Bikeway from the Goodwill Bridge to the area behind 1William Street. It will also include construction of a 450 metre walkway above the Brisbane River.

Waterline Park and the Goodwill Extension area upgrade work is expected to be completed by late-2019.

For any construction, employment or supply opportunities related to this package of work please contact Multiplex direct on 1800 931 760 or email queenswharfbrisbane@multiplex.global.

Later this year Destination Brisbane Consortium will go to tender for the main integrated resort development. More information on this process and how you can be involved will be advised through our website and monthly newsletter.

Construction Map

In mid-2018 Destination Brisbane Consortium established a project information page with the Industry Capability Network (ICN). To stay informed about work packages, please visit the ICN website at www.queenswharf.icn.org.au.

Construction notices detailing any work occurring outside the site boundary or outside normal hours are uploaded to our website under the Construction page, however you can also subscribe for automatic email updates via our ‘stay informed’ icon on the top right corner of this page.

Destination Brisbane Consortium is excited to be building this transformational city changing project for Brisbane and we thank the community for their patience while this work is undertaken.

For general enquiries please contact the consortium direct on 1800 104 535 or email qwbenquiries@destinationbrisbane.com.au.

 

 

Construction updates

  1. In Progress

    Construction site fencing and offices to be installed ahead of Foreshore South works

    An area adjacent to the Bicentennial Bikeway, near the Goodwill Bridge, as well as where Waterline Park will be constructed, will be fenced off and site offices installed. When and…
  2. In Progress

    Bicentennial Bikeway upgrade requires temporary diversion – effective 16 July 2018

    The Bicentennial Bikeway from the Goodwill Bridge to the area behind 1 William Street will be closed for 12 months to allow upgrade works. When and where: From 5am…
  3. In Progress

    Night-time truck movements to be introduced from 4 June

    Probuild will soon begin hauling material from site between 6.30pm and 2am Monday to Saturday. The move to night haulage will mean less trucks required on the road during the…
  4. In Progress

    Building you a better bikeway

    From Monday 16 July 2018 to mid-2019 the Bicentennial Bikeway from  near the Goodwill Bridge to the back of 1 William Street will  be under construction. When complete, the 500 metre section…
  5. Completed

    Two lane closure on Margaret Street, between William and George Streets

    On Saturday 23 June 2018 two of the four lanes will be temporarily closed while construction work occurs along the footpath and site hoarding. When: On Saturday 23 June,…
  6. Completed

    Electrical conduit installation along the Bicentennial Bikeway

    From Monday 11 June to Friday 22 June 2018, Multiplex will complete the installation of power and security feeds to temporary construction facilities. When: From Monday 11 June to Friday…
  7. Completed

    Gardens Point Rd and footpath upgrades

    From Wednesday 16 May until Friday 8 June, Multiplex will begin construction work to make Gardens Point Rd and its adjacent pedestrian footpath suitable for Bicentennial Bikeway temporary pedestrian and…
  8. Completed

    New work area: Geotechnical drilling at various locations along the Bicentennial Bikeway and future Waterline Park location

    From Tuesday 1 May to Tuesday 15 May 2018, Multiplex will begin investigative work that includes geotechnical drilling to inform construction methodology for the future works. When: From Tuesday 1…
  9. Completed

    Temporary single lane closure on Margaret Street, between William and George Streets

    For three (3) weeks from Monday 30 April to Monday 21 May 2018 the far-left lane of Margaret Street will be closed to enable a safe exclusion zone while excavation…
  10. Completed

    Two lane closure on Margaret Street, between George and William Streets

    Night works: From 7pm Wednesday 14 March until 5am Thursday 15 March two lanes will be closed along a section of Margaret Street to undertake maintenance works on water main…