Construction

Multiple contractors appointed to $3.6B Queen’s Wharf Brisbane integrated resort development.

Destination Brisbane Consortium officially won the right to develop Queen’s Wharf Brisbane in October 2015 and since that time has undertaken a detailed approval process with the Queensland Government for its Plan of Development on the site.

In January 2017 work began onsite with the temporary closure of part of William Street to enable demolition of three non-heritage government buildings. Following that, more than 400,000m3 of material was removed from site making it the largest civil excavation project in Queensland.

Now, after more than three years on site, we are now starting to see the integrated resort development basement structure come up out of the ground and later this year (2020) we expect to see the four towers well above George Street.

Construction of the main integrated resort development including four towers and public space is being done by principal contractor Multiplex. For more information about construction, employment and supply opportunities please contact Multiplex direct on 1800 931 760 or email queenswharfbrisbane@multiplex.global.

Maritime work in the Brisbane River is well advanced and will eventually provide 6,500m2 of new public space to be known as The Landing.  These works are being undertaken by Probuild and for construction, employment or supply opportunities please contact Probuild direct on 1800 676 329 or email: queenswharf@probuild.com.au.

Early works for construction of the Neville Bonner (pedestrian) Bridge commenced in March 2020 on the South Bank side of the river and will be complete in time for the integrated resort development opening in late-2022. Fitzgerald Constructions Australia has been engaged to undertake the bridge works. For construction, employment or supply opportunities please contact them direct at queenswharf@fitzgeraldconstructions.com.au or on 1800 413 951.

Current construction hours are from 6.30am to 6.30pm Monday to Saturday. For occasions when work is required outside these hours, construction notices are issued.

To stay informed about the project and construction activities please subscribe to our monthly e-newsletter or sign-up for construction updates by following the stay informed tab at the top of this page.

Destination Brisbane Consortium is excited to be building this transformational city changing project for Brisbane and we thank the community for their patience while this work is undertaken.

For general enquiries please contact the Consortium direct on 1800 104 535 or email qwbenquiries@destinationbrisbane.com.au.

Construction updates

  1. In Progress

    Night works for material load-out on George Street

    From 19 July 2021 for four weeks, night works will be required for removal of non-heritage material from the Printery Building. Each night, a temporary loading bay will be established…
  2. In Progress

    Future public realm requires vegetation removal along the Bicentennial Bikeway and in Miller Park

    In three work stages starting 6 July 2021 vegetation, including many invasive species, will be removed from areas adjacent to the Bicentennial Bikeway and in Miller Park. When: From 6…
  3. In Progress

    Stephens Lane to close to pedestrian and vehicular access

    From 21 June 2021 Stephens Lane will be closed for vehicle and pedestrian access. It will reopen as a walkway in late-2022 with the integrated resort development. When: From Monday…
  4. In Progress

    Extended night works: Structural steel and precast concrete installation

    Night works will continue through to 24 September 2021, five nights a week. For safety reasons large exclusion zones are required for these works when minimal workers are on-site.
  5. In Progress

    Construction zone extending to include Miller Park and Queens Wharf Road – no pedestrian access allowed

    From Monday 22 March 2021 Miller Park and Queens Wharf Road will be fenced and closed for public access while construction works are underway. Please use alternative routes. When:…
  6. In Progress

    Construction zone to include Queens Wharf Road – no motorcycle parking permitted

    From Tuesday 2 March 2021 construction will begin along Queens Wharf Rd. Motorcycle parking will be removed progressively from this date. Access maintained for authorised vehicles only. When: From Tuesday…
  7. In Progress

    Revised: Bicentennial Bikeway upgrade between North Quay terminal and The Cove

    From 3 September 2020 the Bicentennial Bikeway width will be reduced to 3 metres to enable upgrade works to begin. When: Construction work along the bikeway will occur from…
  8. In Progress

    Site establishment at South Bank for bridge

    On Monday 2 March Fitzgerald Constructions Australia will start early works at South Bank to enable the start of construction on the Neville Bonner Bridge When: From Monday 2 March…
  9. In Progress

    Temporary traffic changes to part of George Street (between Mary and Margaret Streets)

    From Monday 26 August 2019 materials will be lifted from trucks on George Street into the Queen’s Wharf construction site. For safety reasons, temporary traffic holds will be required on…
  10. Scheduled

    Temporary lane closure for material load-out on George Street

    From 2 August 2021 for four weeks, works will be required for removal of non-heritage material from the Printery Building. A temporary loading bay will be established on George Street…
  11. Scheduled

    Temporary detour at South Bank while overhead works restrict access to Clem Jones Promenade

    On Wednesday 28 and Thursday 29 July 2021 precast concrete will be installed on the Neville Bonner Bridge deck that spans the Clem Jones Promenade. When: On Wednesday 28 July…