Construction Updates

Complete

On Saturday 15 January 2022, out-of-hours works and a temporary traffic detour will be required to climb a tower crane

Complete

From 3 September 2020 the Bicentennial Bikeway width will be reduced to 3 metres to enable upgrade works to begin.

Complete

DATE UPDATED (due to weather): On Saturday 4 December to Sunday 5 December 2021, out-of-hours works and traffic detour in

Complete

Out-of-hours work is required carry out the installation of bridge modules. When: Night works: From Sunday 21 November to Tuesday

Complete

Updated: On Wednesday 27 October 2021, the Clem Jones Promenade in front of The Wheel of Brisbane, will be temporarily

Complete

Rescheduled to 24 October: out-of-hours work is required to bring a number of concrete trucks into the bridge construction zone

Complete

In three work stages starting 6 July 2021 vegetation, including many invasive species, will be removed from areas adjacent to

Complete

Night works will continue through to 24 September 2021, five nights a week. For safety reasons large exclusion zones are

Complete

George Street, between Charlotte and Margaret Streets will be closed to traffic in one or both directions, at night, for

Complete

Between Tuesday 14th and Wednesday 15th September 2021 underslung service works will be installed on the Neville Bonner Bridge deck

Complete

Over the weekend of Saturday 11 and Sunday 12 September 2021, out-of-hours works and a temporary traffic detour will be

Complete

On Thursday 9 September 2021 a concrete pour will occur on the Neville Bonner Bridge deck section that spans the

Complete

Revised dates: From Sunday 22 August 2021, nights work and temporary traffic detours will be required to upgrade stormwater connections

Complete

From 19 July 2021 for four weeks, night works will be required for removal of non-heritage material from the Printery

Complete

From 2 August 2021 for four weeks, works will be required for removal of non-heritage material from the Printery Building.

Complete

On Wednesday 28 and Thursday 29 July 2021 precast concrete will be installed on the Neville Bonner Bridge deck that

Complete

A significant section of the Neville Bonner Bridge will be lifted into position above the expressway requiring a weekend closure

Complete

A temporary gantry to be installed as a safety measure for when the bridge deck section is lifted in over

Complete

On Tuesday 15 June 2021 the first section of bridge will be installed from the South Bank abutment to a

Complete

Night works will continue through to Monday 31 May 2021, five nights a week. Night works are required to install