Construction Updates
Back

Temporary traffic changes on North Quay affecting motorcycle parking

From 20 January until 30 September 2019 a sewer line will be installed and connected at North Quay. One traffic lane (and partial merge lane) and the footpath will be closed during these works. Alternative motorcycle parking is available and two lanes will remain open.

When:

From 8pm, Sunday 20 January 2019* until Monday 30 September 2019 essential services work will be undertaken to install an underground sewer main and connect it with the existing Queensland Urban Utilities services.

Where:

The connection point for the services and retrieval location for the tunnel boring machine will be on North Quay, between Tank and Ann Streets. This means the furthest right lane (and partial merge lane) and footpath, in the direction of travel (southward), will be temporarily closed for this short section. All normal traffic movements will be possible with two lanes remaining open.

Motorcycle parking on the river side footpath of North Quay will be closed during the work. Alternative motorcycle parking spaces (like for like number) have been allocated on William Street and Queens Wharf Rd. See attached map.

A full list of motorcycle parking locations is available on Council’s website https://www.brisbane.qld.gov.au/traffic-transport/parking-brisbane/parking-brisbane-cbd/inner-city-motorcycle-parking

*Work is planned to commence from this date pending approvals.

What to expect:

From 8pm on Sunday 20 January, traffic control will close far right lane (and partial merge lane) on North Quay between Tank and Ann Streets and the adjacent footpath and motorcycle parks.

Traffic control will be in place as well as digital a VMS board on North Quay providing warning to the impending lane closure. For more information about traffic conditions and changes visit www.131940.qld.gov.au or call 13 19 40.