Construction

Multiple contractors appointed to $3.6B Queen’s Wharf Brisbane integrated resort development.

Destination Brisbane Consortium officially won the right to develop Queen’s Wharf Brisbane in October 2015 and since that time has undertaken a detailed approval process with the Queensland Government for its Plan of Development on the site.

In January 2017 work began onsite with the temporary closure of part of William Street to enable demolition of three non-heritage government buildings. Following that, more than 400,000m3 of material was removed from site making it the largest civil excavation project in Queensland.

Now, after more than three years on site, we are now starting to see the integrated resort development basement structure come up out of the ground and later this year (2020) we expect to see the four towers well above George Street.

Construction of the main integrated resort development including four towers and public space is being done by principal contractor Multiplex. For more information about construction, employment and supply opportunities please contact Multiplex direct on 1800 931 760 or email queenswharfbrisbane@multiplex.global.

Maritime work in the Brisbane River is well advanced and will eventually provide 6,500m2 of new public space to be known as The Landing.  These works are being undertaken by Probuild and for construction, employment or supply opportunities please contact Probuild direct on 1800 676 329 or email: queenswharf@probuild.com.au.

Early works for construction of the Neville Bonner (pedestrian) Bridge commenced in March 2020 on the South Bank side of the river and will be complete in time for the integrated resort development opening in late-2022. Fitzgerald Constructions Australia has been engaged to undertake the bridge works. For construction, employment or supply opportunities please contact them direct at queenswharf@fitzgeraldconstructions.com.au or on 1800 413 951.

Current construction hours are from 6.30am to 6.30pm Monday to Saturday. For occasions when work is required outside these hours, construction notices are issued.

To stay informed about the project and construction activities please subscribe to our monthly e-newsletter or sign-up for construction updates by following the stay informed tab at the top of this page.

Destination Brisbane Consortium is excited to be building this transformational city changing project for Brisbane and we thank the community for their patience while this work is undertaken.

For general enquiries please contact the Consortium direct on 1800 104 535 or email qwbenquiries@destinationbrisbane.com.au.

Construction updates

  1. In Progress

    Extended: Geotechnical investigations required adjacent to Bicentennial Bikeway

    Early works to investigate ground conditions are in sections adjacent to the Bicentennial Bikeway, which may require some temporary reductions in width, however bikeway access will be maintained at all…
  2. In Progress

    Maritime construction work will require intermittent interruptions to a short section of the Bicentennial Bikeway

    To create a safe work zone, a section of the Bicentennial Bikeway, adjacent to the Finger Wharves, will be intermittently reduced in width and some temporary holds (outside peak commute…
  3. In Progress

    Site establishment at South Bank for bridge

    On Monday 2 March Fitzgerald Constructions Australia will start early works at South Bank to enable the start of construction on the Neville Bonner Bridge When: From Monday 2 March…
  4. In Progress

    Temporary traffic changes to part of George Street (between Mary and Margaret Streets)

    From Monday 26 August 2019 materials will be lifted from trucks on George Street into the Queen’s Wharf construction site. For safety reasons, temporary traffic holds will be required on…
  5. Completed

    Mangrove planting requires minor interruptions to a short section of the Bicentennial Bikeway

    To create a safe work zone, a section of the Bicentennial Bikeway, adjacent to the Finger Wharves, will be intermittently reduced in width while up to 350 mangroves are planted…
  6. Completed

    Geotechnical investigations

    From Sunday 5 July 2020 night work will occur along Margaret Street and then George Street temporarily affecting traffic and pedestrian movements. When: NIGHT WORKS: From 6.30pm until 6.30am each…
  7. Completed

    Geotechnical investigations required adjacent to Bicentennial Bikeway

    Early works to investigate ground conditions are in sections adjacent to the Bicentennial Bikeway, which may require some temporary reductions in width, however bikeway access will be maintained at all…
  8. Completed

    Part of Clem Jones Promenade temporarily closed to enable bridge early works

    On Tuesday 19 May and Wednesday 20 May 2020 early works including vegetation removal will occur at South Bank ahead of construction of the Neville Bonner Bridge. What, when and…
  9. Completed

    Intermittent night works may be required on-site at Queen’s Wharf over the next two months

    At times during May and June 2020 from 6.30pm until 2.30am, some night works may be required on-site to undertake critical work. When: Night works may be undertaken in…
  10. Completed

    Temporary William Street motorcycle parking to close as North Quay motorcycle parking has reopened

    Motorcycle parking along North Quay between Tank and Ann Streets has reopened and the temporary parking on William Street (outside the Commissariat Store) will cease from Monday 20 April.