For selected days between 28 February 2025 until the end of April 2025 an out-of-hours permit is in place to complete isolated critical large concrete delivery for Queens Wharf Brisbane Towers 5 & 6.
Works, expected two days per week, are to take place from 5am on selected days and through traffic will be maintained at all times.
When:
From Friday 28th February 2025 to Wednesday 30th April 2025, from 5am to 6:30am. Normal work permits commence from 6:30am each day.
Where:
William St between Margaret Street and Alice Street, Brisbane City 4000.
What to expect:
- Traffic Control signage establishment
- Through traffic to be maintained
- Concrete pump setup
- Concrete delivery
We apologise for any inconvenience caused and appreciate your ongoing patience.