Extended night works: Structural steel and precast concrete installation

Night works will continue through to 1 April 2022, five nights a week. For safety reasons large exclusion zones are required for these works when minimal workers are on-site.

When:

Night works are scheduled from 6.30pm to 5.30am Monday to Friday nights to 1 April 2022. These works are in addition to the standard site hours from 6.30am to 6.30pm Monday to Saturday. These works have approved permits in place, however, are site and weather dependent.

Where:

Night works will be within the integrated resort development site. William St and Queen’s Wharf Road will be used as loading zones.

What to expect:

At times the following may be noticed:

  • Workers and vehicles including trucks, entering and exiting the site at various times
  • Engine noise from tower cranes when operating
  • Intermittent hammering on steel and rattle gun noise
  • Portable lighting directed at work areas.